November Highway Maintenance Report
·
Completed ditch
work on
·
Start winter
road-side brush cutting with mower
·
Graveled
turn-a-rounds on Stanton and Mack Roads
·
Patched Rocky
Ridge and West Galway Roads with gravel
·
Completed
shoulder work on
·
Patched potholes
·
Sandblasted dump
body on Truck #8 in preparation for rebuild
·
Plowed and sanded
– 3 times
Scheduled December Highway Maintenance
·
Plow and sand as
needed
·
Continue road-side
brush cutting on R.O.W. with tractor
·
Continue work on
Truck #8
o
Rebuilding dump
body