June Highway Maintenance Report
·
Continued work on
·
Continued mowing
the ROW’s (town-wide)
·
Screened gravel
(3,000 yds.)
·
Removed trees,
top soiled and prepared site for fence installation at the Town Hall
·
Poured cement pad
in preparation for the installation of the back-up generator as well as the
sonotubes for the electrical board kiosk
·
Paved with the
Town of
Scheduled July Highway Maintenance
·
Continue road
work on
·
Paving
·
Start
reconstruction work on second half of
·
Continue mowing
the ROW’s (town-wide)